PDF download · PRINCE2 Agile Foundation

Free PRINCE2 Agile Foundation Practice Test PDF

Download a free PRINCE2 Agile Foundation practice test PDF with 30 questions, answers and explanations, then continue with online mock exams.

Free sample · PRINCE2 Agile FoundationQ1
In the Directing a Project process, which of the following does the project board authorise?
Correct — A. It is the project board's role to sanction both project initiation and project closure. Why the other options are incorrect: • Day-to-day work package assignments: Authorising day-to-day work packages falls within the project manager's remit, not the board's. • Quality assurance inspections: Quality inspections are not part of the directing process and are not a board-level activity. • Granular team-level plans: Detailed team-level plans are the responsibility of team managers, not the board. • Actions taken to respond to risks: Managing and enacting risk responses is the project manager's responsibility.
↑ Tap an answer to check it
Download

Free PRINCE2 Agile Foundation PDF with 30 questions

Print it, save it, or use it as a quick cram sheet before taking a timed mock exam.

Download PDF

The PDF includes 30 PRINCE2 Agile Foundation questions with answers and explanations.

Sample questions

Try PRINCE2 Agile Foundation questions now

  1. Q1In the Directing a Project process, which of the following does the project board authorise?

    Show answer

    ✓ Correct answer: Initiation and closure of the project

    It is the project board's role to sanction both project initiation and project closure. Why the other options are incorrect: • Day-to-day work package assignments: Authorising day-to-day work packages falls within the project manager's remit, not the board's. • Quality assurance inspections: Quality inspections are not part of the directing process and are not a board-level activity. • Granular team-level plans: Detailed team-level plans are the responsibility of team managers, not the board. • Actions taken to respond to risks: Managing and enacting risk responses is the project manager's responsibility.

    Open the full explanation page →

  2. Q2What best explains why a Business Case may need to be revised during a project?

    Show answer

    ✓ Correct answer: The project environment and costs can evolve

    A Business Case must be revised when underlying assumptions, costs, risks, or anticipated benefits alter during the project. Why the other options are incorrect: • To ensure the project delivers success: No project management methodology can guarantee a successful outcome. • To reduce the involvement of stakeholders: Stakeholders continue to play an essential role irrespective of whether the Business Case is updated. • To do away with project controls: Project controls remain in force even when the Business Case is revised. • To streamline the team structure: Team structure is a matter for the Organization theme and is unrelated to Business Case updates.

    Open the full explanation page →

  3. Q3Which of the following does NOT form part of Controlling a Stage?

    Show answer

    ✓ Correct answer: Approving the final closure of the project

    Final project closure is addressed within the Closing a Project process and lies outside the scope of Controlling a Stage. Why the other options are incorrect: • Tracking stage progress: Tracking progress is one of the central purposes of this process. • Managing issues that arise: Managing issues as they emerge is the project manager's responsibility within this process. • Providing regular progress reports: Regular stage progress reporting is a standard output of this process. • Taking corrective action when needed: Taking corrective action to maintain stage tolerances is an integral part of stage control.

    Open the full explanation page →

  4. Q4Which role is responsible for identifying and advising on risks that suppliers pose to delivery schedules?

    Show answer

    ✓ Correct answer: Senior supplier

    The senior supplier identifies supplier-related risks that could affect delivery schedules and advises the project accordingly. Why the other options are incorrect: • Executive: The executive ensures the project remains strategically aligned but is not responsible for supplier scheduling risks. • Senior user: The senior user is focused on outcomes and benefits rather than on supplier scheduling risks. • Project assurance: Project assurance monitors whether processes are followed but does not own risk identification or advice. • Project support: Project support handles administrative functions and does not provide risk guidance.

    Open the full explanation page →

  5. Q5Under what circumstances might additional management stages be introduced?

    Show answer

    ✓ Correct answer: When greater control is needed on complex projects

    On more complex projects, adding extra stages is a way of increasing management control. Why the other options are incorrect: • To reduce the amount of planning required: Adding stages increases the amount of planning required, not reduces it. • To ensure the project closes sooner: More stages do not lead to earlier project closure. • To decrease the number of reviews: Each additional stage introduces another review point, increasing rather than decreasing the number of reviews. • To avoid the need for Project Board decisions: The Project Board retains its decision-making role regardless of how many stages exist.

    Open the full explanation page →

  6. Q6What information does a work package typically contain?

    Show answer

    ✓ Correct answer: The work's scope, permitted variances, and reporting obligations

    A work package sets out the scope of the assigned work alongside the tolerances and reporting requirements applicable to it. Why the other options are incorrect: • A detailed business case together with expected benefits: Business case content and benefits realisation planning are held in separate documents. • The strategic objectives of the corporate portfolio: Corporate portfolio objectives are defined at an organisational level above the project. • The criteria for final project acceptance: Project-level acceptance criteria are documented in the project product description. • The content and timing of stage boundary reviews: Stage boundary review content is addressed through the managing a stage boundary process, not work packages.

    Open the full explanation page →

Unlock everything

Full PRINCE2 Agile Foundation bank + unlimited mocks

Try 30 questions free. Unlock the complete PRINCE2 Agile Foundation question bank, every explanation, and unlimited timed mock exams. Practice on any device.

Unlock PRINCE2 Agile Foundation →
Cramming?
$2.99
/ week · per exam
Best value
$6.99
/ month · per exam