Which role is responsible for identifying and advising on risks that suppliers pose to delivery schedules?
Practise this PRINCE2 Agile Foundation question free, then download the PDF, watch the video walkthrough, or unlock timed mock exams for the full web bank.
✓ Correct answer: A. Senior supplierThe senior supplier identifies supplier-related risks that could affect delivery schedules and advises the project accordingly.
Why the other options are incorrect:
• Executive: The executive ensures the project remains strategically aligned but is not responsible for supplier scheduling risks.
• Senior user: The senior user is focused on outcomes and benefits rather than on supplier scheduling risks.
• Project assurance: Project assurance monitors whether processes are followed but does not own risk identification or advice.
• Project support: Project support handles administrative functions and does not provide risk guidance.
Keep practising. Use the free PRINCE2 Agile Foundation PDF, watch the YouTube walkthrough, or unlock all 10 web questions with timed mock exams.
Free practice here. Timed mocks when you are ready.
Study the PRINCE2 Agile Foundation free question explanations, download the PDF, then unlock timed mock exams on the web when you want exam-day practice.