What best explains why a Business Case may need to be revised during a project?
Practise this PRINCE2 Agile Foundation question free, then download the PDF, watch the video walkthrough, or unlock timed mock exams for the full web bank.
✓ Correct answer: A. The project environment and costs can evolveA Business Case must be revised when underlying assumptions, costs, risks, or anticipated benefits alter during the project.
Why the other options are incorrect:
• To ensure the project delivers success: No project management methodology can guarantee a successful outcome.
• To reduce the involvement of stakeholders: Stakeholders continue to play an essential role irrespective of whether the Business Case is updated.
• To do away with project controls: Project controls remain in force even when the Business Case is revised.
• To streamline the team structure: Team structure is a matter for the Organization theme and is unrelated to Business Case updates.
Keep practising. Use the free PRINCE2 Agile Foundation PDF, watch the YouTube walkthrough, or unlock all 10 web questions with timed mock exams.
Free practice here. Timed mocks when you are ready.
Study the PRINCE2 Agile Foundation free question explanations, download the PDF, then unlock timed mock exams on the web when you want exam-day practice.