What information does a work package typically contain?

Practise this PRINCE2 Agile Foundation question free, then download the PDF, watch the video walkthrough, or unlock timed mock exams for the full web bank.
Download PDFWatch video
Multiple choice — select the best answer
✓ Correct answer: A. The work's scope, permitted variances, and reporting obligations A work package sets out the scope of the assigned work alongside the tolerances and reporting requirements applicable to it. Why the other options are incorrect: • A detailed business case together with expected benefits: Business case content and benefits realisation planning are held in separate documents. • The strategic objectives of the corporate portfolio: Corporate portfolio objectives are defined at an organisational level above the project. • The criteria for final project acceptance: Project-level acceptance criteria are documented in the project product description. • The content and timing of stage boundary reviews: Stage boundary review content is addressed through the managing a stage boundary process, not work packages.

Keep practising. Use the free PRINCE2 Agile Foundation PDF, watch the YouTube walkthrough, or unlock all 10 web questions with timed mock exams.

Free PDFVideo walkthrough
Keep practising

Related questions

Free practice here. Timed mocks when you are ready.

Study the PRINCE2 Agile Foundation free question explanations, download the PDF, then unlock timed mock exams on the web when you want exam-day practice.

Download PDFStart practice test