In the Directing a Project process, which of the following does the project board authorise?
Practise this PRINCE2 Agile Foundation question free, then download the PDF, watch the video walkthrough, or unlock timed mock exams for the full web bank.
✓ Correct answer: A. Initiation and closure of the projectIt is the project board's role to sanction both project initiation and project closure.
Why the other options are incorrect:
• Day-to-day work package assignments: Authorising day-to-day work packages falls within the project manager's remit, not the board's.
• Quality assurance inspections: Quality inspections are not part of the directing process and are not a board-level activity.
• Granular team-level plans: Detailed team-level plans are the responsibility of team managers, not the board.
• Actions taken to respond to risks: Managing and enacting risk responses is the project manager's responsibility.
Keep practising. Use the free PRINCE2 Agile Foundation PDF, watch the YouTube walkthrough, or unlock all 10 web questions with timed mock exams.