Under what circumstances might additional management stages be introduced?
Practise this PRINCE2 Agile Foundation question free, then download the PDF, watch the video walkthrough, or unlock timed mock exams for the full web bank.
AWhen greater control is needed on complex projects
BTo reduce the amount of planning required
CTo ensure the project closes sooner
DTo decrease the number of reviews
ETo avoid the need for Project Board decisions
✓ Correct answer: A. When greater control is needed on complex projectsOn more complex projects, adding extra stages is a way of increasing management control.
Why the other options are incorrect:
• To reduce the amount of planning required: Adding stages increases the amount of planning required, not reduces it.
• To ensure the project closes sooner: More stages do not lead to earlier project closure.
• To decrease the number of reviews: Each additional stage introduces another review point, increasing rather than decreasing the number of reviews.
• To avoid the need for Project Board decisions: The Project Board retains its decision-making role regardless of how many stages exist.
Keep practising. Use the free PRINCE2 Agile Foundation PDF, watch the YouTube walkthrough, or unlock all 10 web questions with timed mock exams.
Free practice here. Timed mocks when you are ready.
Study the PRINCE2 Agile Foundation free question explanations, download the PDF, then unlock timed mock exams on the web when you want exam-day practice.