The project board instructs the project manager to capture lessons from an ongoing project and feed them into a similar project starting soon. Which principle is this?
Practise this PRINCE2 Practitioner question free, then download the PDF, watch the video walkthrough, or unlock timed mock exams for the full web bank.
✓ Correct answer: A. Learn from experienceSharing lessons during a project allows them to be applied immediately elsewhere, demonstrating the 'learn from experience' principle.
Why the other options are incorrect:
• Manage by exception: Exception management is about controlling deviations, not sharing lessons.
• Tailor to suit the project: Tailoring is about adapting the method, not knowledge transfer.
• Ensure continued business justification: Business justification relates to viability, not lessons.
• Focus on products: Product focus is about deliverables, not lessons learned.
Keep practising. Use the free PRINCE2 Practitioner PDF, watch the YouTube walkthrough, or unlock all 10 web questions with timed mock exams.
Free practice here. Timed mocks when you are ready.
Study the PRINCE2 Practitioner Exam 2026 free question explanations, download the PDF, then unlock timed mock exams on the web when you want exam-day practice.