A new transport ticketing system project sets detailed quality criteria for each product before any development work starts. Which statement explains why this supports governance?
Practise this PRINCE2 Practitioner question free, then download the PDF, watch the video walkthrough, or unlock timed mock exams for the full web bank.
CIt prevents the project manager from delegating work
DIt removes the need for highlight reports
EIt guarantees the project will finish early
✓ Correct answer: A. It ensures outputs meet agreed quality standardsDefining quality criteria before work starts ensures that outputs can be tested and accepted objectively.
Why the other options are incorrect:
• It avoids the need for supplier involvement: Suppliers may still be involved in delivery.
• It prevents the project manager from delegating work: Delegation is still possible once criteria are set.
• It removes the need for highlight reports: Highlight reports are still required for progress tracking.
• It guarantees the project will finish early: Setting criteria supports quality, not guaranteed early delivery.
Keep practising. Use the free PRINCE2 Practitioner PDF, watch the YouTube walkthrough, or unlock all 10 web questions with timed mock exams.
Free practice here. Timed mocks when you are ready.
Study the PRINCE2 Practitioner Exam 2026 free question explanations, download the PDF, then unlock timed mock exams on the web when you want exam-day practice.