Video walkthrough · PRINCE2 Practitioner

PRINCE2 Practitioner Practice Test Video

Watch the PRINCE2 Practitioner practice test video walkthrough, review the questions, download the free PDF and start an online mock exam.

Free sample · PRINCE2 PractitionerQ1
A new transport ticketing system project sets detailed quality criteria for each product before any development work starts. Which statement explains why this supports governance?
Correct — A. Defining quality criteria before work starts ensures that outputs can be tested and accepted objectively. Why the other options are incorrect: • It avoids the need for supplier involvement: Suppliers may still be involved in delivery. • It prevents the project manager from delegating work: Delegation is still possible once criteria are set. • It removes the need for highlight reports: Highlight reports are still required for progress tracking. • It guarantees the project will finish early: Setting criteria supports quality, not guaranteed early delivery.
↑ Tap an answer to check it
Watch & learn

PRINCE2 Practitioner exam — full Q&A walkthrough

Every question read aloud with the answer explained. Play it on your commute, then test yourself.

Sample questions

Try PRINCE2 Practitioner questions now

  1. Q1A new transport ticketing system project sets detailed quality criteria for each product before any development work starts. Which statement explains why this supports governance?

    Show answer

    ✓ Correct answer: It ensures outputs meet agreed quality standards

    Defining quality criteria before work starts ensures that outputs can be tested and accepted objectively. Why the other options are incorrect: • It avoids the need for supplier involvement: Suppliers may still be involved in delivery. • It prevents the project manager from delegating work: Delegation is still possible once criteria are set. • It removes the need for highlight reports: Highlight reports are still required for progress tracking. • It guarantees the project will finish early: Setting criteria supports quality, not guaranteed early delivery.

    Open the full explanation page →

  2. Q2A team member documents a new risk management technique discovered during the project for future use. Which principle is this?

    Show answer

    ✓ Correct answer: Learn from experience

    Capturing new techniques for future use demonstrates the 'learn from experience' principle. Why the other options are incorrect: • Focus on products: Product focus is about defining deliverables, not capturing techniques. • Tailor to suit the project: Tailoring is about adapting methods, not recording new ones for future. • Manage by exception: Exception management is about tolerances, not learning. • Ensure continued business justification: Business justification ensures viability, not recording lessons.

    Open the full explanation page →

  3. Q3During stage boundary assessment, the project manager updates the business case. Which statement explains why this is appropriate?

    Show answer

    ✓ Correct answer: To confirm the project remains viable before authorising the next stage

    Stage boundaries are key points to reassess viability and update the business case accordingly. Why the other options are incorrect: • To ensure product descriptions are up to date: Product descriptions may be updated, but the key point is viability review. • To meet the senior supplier’s reporting needs: Supplier reporting needs are addressed in communication management, not business case updates. • To reduce the number of highlight reports: Highlight reports are unrelated to business case updates. • To comply with corporate budgeting cycles: Corporate budgeting cycles may influence timing but are not the primary reason.

    Open the full explanation page →

  4. Q4Which principle requires that a project be stopped if it can no longer be justified?

    Show answer

    ✓ Correct answer: Ensure continued business justification

    The 'ensure continued business justification' principle requires that projects without valid justification should be stopped. Why the other options are incorrect: • Manage by stages: Manage by stages defines review points, not the decision to stop. • Learn from experience: Learning from experience is about applying lessons, not viability decisions. • Tailor to suit the project: Tailoring is about adapting processes, not stopping projects. • Focus on products: Focus on products is about defining deliverables, not continuation decisions.

    Open the full explanation page →

  5. Q5Who is responsible for maintaining the lessons log during the project?

    Show answer

    ✓ Correct answer: Project manager

    The project manager maintains the lessons log and ensures lessons are shared and acted upon. Why the other options are incorrect: • Executive: The executive provides overall direction, not day-to-day log maintenance. • Senior user: The senior user contributes lessons but does not maintain the log. • Senior supplier: The senior supplier contributes technical lessons, not the log upkeep. • Project assurance: Assurance checks the process; it does not own the log.

    Open the full explanation page →

  6. Q6An international conference project shortens its initiation stage to two weeks instead of the usual month, arguing that much of the planning was completed by the event sponsor in advance. Governance products are still produced, but with less formality. Is this consistent with PRINCE2, and why?

    Show answer

    ✓ Correct answer: Yes, because tailoring can shorten stages when justified

    Tailoring allows adjusting stage durations as long as governance requirements are met and justification is documented. Why the other options are incorrect: • Yes, because initiation can be skipped if sponsor work is complete: Initiation cannot be skipped entirely; tailoring must retain governance. • No, because the initiation stage length is fixed in PRINCE2: Stage length is not fixed; it can be adapted. • No, because shortening stages removes governance: Shortening does not remove governance if controls remain. • No, because the project manager cannot change initiation: The project manager can propose changes with approval.

    Open the full explanation page →

Unlock everything

Full PRINCE2 Practitioner bank + unlimited mocks

Try 30 questions free. Unlock the complete PRINCE2 Practitioner question bank, every explanation, and unlimited timed mock exams. Practice on any device.

Unlock PRINCE2 Practitioner →
Cramming?
$2.99
/ week · per exam
Best value
$6.99
/ month · per exam