HomePRINCE2 Practitioner Exam 2026Question 6 of 10
PRINCE2 PractitionerQuestion 6 / 10

An international conference project shortens its initiation stage to two weeks instead of the usual month, arguing that much of the planning was completed by the event sponsor in advance. Governance products are still produced, but with less formality. Is this consistent with PRINCE2, and why?

Practise this PRINCE2 Practitioner question free, then download the PDF, watch the video walkthrough, or unlock timed mock exams for the full web bank.
Download PDFWatch video
Multiple choice — select the best answer
✓ Correct answer: A. Yes, because tailoring can shorten stages when justified Tailoring allows adjusting stage durations as long as governance requirements are met and justification is documented. Why the other options are incorrect: • Yes, because initiation can be skipped if sponsor work is complete: Initiation cannot be skipped entirely; tailoring must retain governance. • No, because the initiation stage length is fixed in PRINCE2: Stage length is not fixed; it can be adapted. • No, because shortening stages removes governance: Shortening does not remove governance if controls remain. • No, because the project manager cannot change initiation: The project manager can propose changes with approval.

Keep practising. Use the free PRINCE2 Practitioner PDF, watch the YouTube walkthrough, or unlock all 10 web questions with timed mock exams.

Free PDFVideo walkthrough
Keep practising

Related questions

Free practice here. Timed mocks when you are ready.

Study the PRINCE2 Practitioner Exam 2026 free question explanations, download the PDF, then unlock timed mock exams on the web when you want exam-day practice.

Download PDFStart practice test