During a supplier-led stage, the project manager notes that quality issues may cause a delay exceeding time tolerance. They alert the project board before the impact is certain. Which statement explains why this is correct under PRINCE2?

Practise this PRINCE2 Practitioner question free, then download the PDF, watch the video walkthrough, or unlock timed mock exams for the full web bank.
Download PDFWatch video
Multiple choice — select the best answer
✓ Correct answer: A. To escalate as soon as a tolerance breach is forecast Manage by exception requires escalation when a tolerance breach is forecast, not only after it occurs. Why the other options are incorrect: • To give the board more regular updates: Regular updates are useful but not the primary reason for escalation. • To ensure the supplier receives instructions: Supplier instructions are managed through the project manager, not escalation triggers. • To avoid completing a checkpoint report: Checkpoint reports are separate from tolerance escalation. • To transfer accountability to the senior supplier: Escalation does not transfer accountability to the senior supplier.

Keep practising. Use the free PRINCE2 Practitioner PDF, watch the YouTube walkthrough, or unlock all 10 web questions with timed mock exams.

Free PDFVideo walkthrough
Keep practising

Related questions

Free practice here. Timed mocks when you are ready.

Study the PRINCE2 Practitioner Exam 2026 free question explanations, download the PDF, then unlock timed mock exams on the web when you want exam-day practice.

Download PDFStart practice test