Which principle requires that a project be stopped if it can no longer be justified?
Practise this PRINCE2 Practitioner question free, then download the PDF, watch the video walkthrough, or unlock timed mock exams for the full web bank.
✓ Correct answer: A. Ensure continued business justificationThe 'ensure continued business justification' principle requires that projects without valid justification should be stopped.
Why the other options are incorrect:
• Manage by stages: Manage by stages defines review points, not the decision to stop.
• Learn from experience: Learning from experience is about applying lessons, not viability decisions.
• Tailor to suit the project: Tailoring is about adapting processes, not stopping projects.
• Focus on products: Focus on products is about defining deliverables, not continuation decisions.
Keep practising. Use the free PRINCE2 Practitioner PDF, watch the YouTube walkthrough, or unlock all 10 web questions with timed mock exams.
Free practice here. Timed mocks when you are ready.
Study the PRINCE2 Practitioner Exam 2026 free question explanations, download the PDF, then unlock timed mock exams on the web when you want exam-day practice.