During stage boundary assessment, the project manager updates the business case. Which statement explains why this is appropriate?
Practise this PRINCE2 Practitioner question free, then download the PDF, watch the video walkthrough, or unlock timed mock exams for the full web bank.
ATo confirm the project remains viable before authorising the next stage
BTo ensure product descriptions are up to date
CTo meet the senior supplier’s reporting needs
DTo reduce the number of highlight reports
ETo comply with corporate budgeting cycles
✓ Correct answer: A. To confirm the project remains viable before authorising the next stageStage boundaries are key points to reassess viability and update the business case accordingly.
Why the other options are incorrect:
• To ensure product descriptions are up to date: Product descriptions may be updated, but the key point is viability review.
• To meet the senior supplier’s reporting needs: Supplier reporting needs are addressed in communication management, not business case updates.
• To reduce the number of highlight reports: Highlight reports are unrelated to business case updates.
• To comply with corporate budgeting cycles: Corporate budgeting cycles may influence timing but are not the primary reason.
Keep practising. Use the free PRINCE2 Practitioner PDF, watch the YouTube walkthrough, or unlock all 10 web questions with timed mock exams.
Free practice here. Timed mocks when you are ready.
Study the PRINCE2 Practitioner Exam 2026 free question explanations, download the PDF, then unlock timed mock exams on the web when you want exam-day practice.