ATo track actual performance against the project plan
BTo define the business benefits and project justification
CTo set out approaches to risk management
DTo establish quality criteria for project products
ETo outline procedures for handling changes
✓ Correct answer: A. To track actual performance against the project planThe Progress theme tracks how actual delivery compares with the plan and provides the means to control the project.
Why the other options are incorrect:
• To define the business benefits and project justification: Establishing business justification falls under the Business Case theme.
• To set out approaches to risk management: Risk management approaches are addressed by the Risk theme.
• To establish quality criteria for project products: Product quality criteria are the concern of the Quality theme.
• To outline procedures for handling changes: Change control procedures belong to the Change theme.
Keep practising. Use the free PRINCE2 Agile Foundation PDF, watch the YouTube walkthrough, or unlock all 10 web questions with timed mock exams.
Free practice here. Timed mocks when you are ready.
Study the PRINCE2 Agile Foundation free question explanations, download the PDF, then unlock timed mock exams on the web when you want exam-day practice.