In which document would you find the evidence supporting a project's business justification?
Practise this PRINCE2 Agile Foundation question free, then download the PDF, watch the video walkthrough, or unlock timed mock exams for the full web bank.
✓ Correct answer: A. The Business CaseThe Business Case is the document that sets out and maintains the evidence for why the project is justified.
Why the other options are incorrect:
• A Work Package: Work Packages define the work to be carried out and do not contain business justification evidence.
• The Issue Register: The Issue Register records problems and concerns raised during the project, not justification evidence.
• The Risk Register: The Risk Register is used to track and manage risks, not to hold evidence of the business justification.
• The Team Plan: Team Plans address how work will be delivered at an operational level and are not justification documents.
Keep practising. Use the free PRINCE2 Agile Foundation PDF, watch the YouTube walkthrough, or unlock all 10 web questions with timed mock exams.
Free practice here. Timed mocks when you are ready.
Study the PRINCE2 Agile Foundation free question explanations, download the PDF, then unlock timed mock exams on the web when you want exam-day practice.