Senior managers consider a project to have succeeded, while end users view it as a failure. What does this divergence suggest?

Practise this APM PMQ question free, then download the PDF, watch the video walkthrough, or unlock timed mock exams for the full web bank.
Download PDFWatch video
Multiple choice — select the best answer
✓ Correct answer: A. The success criteria were not agreed upon or applied consistently across all stakeholder groups When different groups disagree on whether a project succeeded, it points to success criteria that were either poorly defined or applied inconsistently across stakeholder groups. Why the other options are incorrect: • The technical quality of the project's deliverables was inadequate: A lack of technical quality is not implied by this scenario. • The project spent more than its allocated budget: There is no indication in this scenario that the budget was exceeded. • The project's governance arrangements failed to function properly: Ineffective governance is not what this situation primarily illustrates. • The selected project lifecycle was not suited to this project: The choice of project lifecycle is unrelated to the divergence in judgements.

Keep practising. Use the free APM PMQ PDF, watch the YouTube walkthrough, or unlock all 10 web questions with timed mock exams.

Free PDFVideo walkthrough
Keep practising

Related questions

Free practice here. Timed mocks when you are ready.

Study the APM PMQ Exam Prep 2026 free question explanations, download the PDF, then unlock timed mock exams on the web when you want exam-day practice.

Download PDFStart practice test