AThe success criteria were not agreed upon or applied consistently across all stakeholder groups
BThe technical quality of the project's deliverables was inadequate
CThe project spent more than its allocated budget
DThe project's governance arrangements failed to function properly
EThe selected project lifecycle was not suited to this project
✓ Correct answer: A. The success criteria were not agreed upon or applied consistently across all stakeholder groupsWhen different groups disagree on whether a project succeeded, it points to success criteria that were either poorly defined or applied inconsistently across stakeholder groups.
Why the other options are incorrect:
• The technical quality of the project's deliverables was inadequate: A lack of technical quality is not implied by this scenario.
• The project spent more than its allocated budget: There is no indication in this scenario that the budget was exceeded.
• The project's governance arrangements failed to function properly: Ineffective governance is not what this situation primarily illustrates.
• The selected project lifecycle was not suited to this project: The choice of project lifecycle is unrelated to the divergence in judgements.
Keep practising. Use the free APM PMQ PDF, watch the YouTube walkthrough, or unlock all 10 web questions with timed mock exams.
Free practice here. Timed mocks when you are ready.
Study the APM PMQ Exam Prep 2026 free question explanations, download the PDF, then unlock timed mock exams on the web when you want exam-day practice.