A project delivers strong technical results but has poorly defined governance structures. Which risk is most likely to arise?

Practise this APM PMQ question free, then download the PDF, watch the video walkthrough, or unlock timed mock exams for the full web bank.
Download PDFWatch video
Multiple choice — select the best answer
✓ Correct answer: B. Decisions may be taken without adequate authority or strategic alignment Without strong governance, there is a risk that decisions are made by those without adequate authority and that strategic direction is lost. Why the other options are incorrect: • The team will be incapable of generating technical deliverables: Technical delivery can still proceed effectively even where governance is weak. • The project will inevitably overspend its approved budget: Budget overrun is a possible consequence, not an automatic one. • Stakeholders will become overly involved in day-to-day delivery: Excess stakeholder involvement is not the primary risk described. • The project lifecycle will shift to a purely sequential approach: Governance gaps do not dictate the choice of delivery lifecycle.

Keep practising. Use the free APM PMQ PDF, watch the YouTube walkthrough, or unlock all 10 web questions with timed mock exams.

Free PDFVideo walkthrough
Keep practising

Related questions

Free practice here. Timed mocks when you are ready.

Study the APM PMQ Exam Prep 2026 free question explanations, download the PDF, then unlock timed mock exams on the web when you want exam-day practice.

Download PDFStart practice test