AA project whose deliverables are delayed because of technical problems
BA project that produces outputs which do not support the organisation's strategic goals
CA project that goes over budget as a result of supplier pricing
DA project that encounters opposition from stakeholders
EA project that is held up by regulatory requirements
✓ Correct answer: B. A project that produces outputs which do not support the organisation's strategic goalsFor a project to be strategically aligned, its outputs must actively contribute to the organisation's objectives.
Why the other options are incorrect:
• A project whose deliverables are delayed because of technical problems: Being late does not indicate strategic misalignment.
• A project that goes over budget as a result of supplier pricing: Exceeding budget does not reflect a lack of strategic alignment.
• A project that encounters opposition from stakeholders: Stakeholder opposition does not necessarily indicate misalignment with strategy.
• A project that is held up by regulatory requirements: Regulatory delays are an external factor, not a sign of strategic misalignment.
Keep practising. Use the free APM PMQ PDF, watch the YouTube walkthrough, or unlock all 10 web questions with timed mock exams.
Free practice here. Timed mocks when you are ready.
Study the APM PMQ Exam Prep 2026 free question explanations, download the PDF, then unlock timed mock exams on the web when you want exam-day practice.