A project is on time and within budget, yet it is unclear who holds the authority to approve a significant change to scope. What governance problem does this most likely indicate?
Practise this APM PMQ question free, then download the PDF, watch the video walkthrough, or unlock timed mock exams for the full web bank.
EProject controls that are excessively restrictive
✓ Correct answer: A. Poorly defined decision-making authorityA core requirement of governance is that it clearly defines who is authorised to make significant decisions; without this, critical choices cannot be made in a controlled way.
Why the other options are incorrect:
• Inadequate monitoring of project performance: Performance monitoring is working adequately here; the problem is that approval authority is not clearly assigned.
• Insufficient tracking of project benefits: The scenario does not point to any issue with tracking benefits.
• Failure to identify relevant project risks: Identifying risks more thoroughly would not resolve the question of who can approve scope changes.
• Project controls that are excessively restrictive: The concern is that controls are ambiguous, not that they are too tight.
Keep practising. Use the free APM PMQ PDF, watch the YouTube walkthrough, or unlock all 10 web questions with timed mock exams.
Free practice here. Timed mocks when you are ready.
Study the APM PMQ Exam Prep 2026 free question explanations, download the PDF, then unlock timed mock exams on the web when you want exam-day practice.