A project carries on even though it has ceased to support the organisation's business objectives. What does this reveal about the success criteria that were set?

Practise this APM PMQ question free, then download the PDF, watch the video walkthrough, or unlock timed mock exams for the full web bank.
Download PDFWatch video
Multiple choice — select the best answer
✓ Correct answer: B. The criteria failed to align with the organisation's strategic direction For a project to remain relevant, its success criteria need to reflect and adapt to the organisation's current strategic priorities. Why the other options are incorrect: • The criteria placed too much emphasis on satisfying stakeholders: An emphasis on stakeholder satisfaction is not the root cause of this situation. • Excessive detail in the criteria made them impractical to use: The level of detail in the success criteria is not what caused the misalignment. • The criteria were entirely grounded in quality metrics: Basing criteria on quality measures is not the underlying problem here. • The project team was not made aware of the success criteria: Whether the criteria were communicated to the team is not the central concern in this scenario.

Keep practising. Use the free APM PMQ PDF, watch the YouTube walkthrough, or unlock all 10 web questions with timed mock exams.

Free PDFVideo walkthrough
Keep practising

Related questions

Free practice here. Timed mocks when you are ready.

Study the APM PMQ Exam Prep 2026 free question explanations, download the PDF, then unlock timed mock exams on the web when you want exam-day practice.

Download PDFStart practice test