PDF download · Solar PV Professional Exam

Free Solar PV Professional Exam Practice Test PDF

Download a free Solar PV Professional Exam practice test PDF with 30 questions, answers and explanations, then continue with online mock exams.

Free sample · Solar PV Professional ExamQ1
According to OSHA requirements, at what height is fall protection required when installing rooftop PV systems?
Correct — D. OSHA requires fall protection for workers at heights of 6 feet or more in construction activities, which includes PV installation on rooftops.
↑ Tap an answer to check it
Download

Free Solar PV Professional Exam PDF with 30 questions

Print it, save it, or use it as a quick cram sheet before taking a timed mock exam.

Download PDF

The PDF includes 30 Solar PV Professional Exam questions with answers and explanations.

Sample questions

Try Solar PV Professional Exam questions now

  1. Q1According to OSHA requirements, at what height is fall protection required when installing rooftop PV systems?

    Show answer

    ✓ Correct answer: 6 feet

    OSHA requires fall protection for workers at heights of 6 feet or more in construction activities, which includes PV installation on rooftops.

    Open the full explanation page →

  2. Q2What is the required minimum bending radius for PV source circuit conductors in conduit as per NEC 2017?

    Show answer

    ✓ Correct answer: At least 8 times the diameter of the conductor

    NEC 2017 specifies that the minimum bending radius for PV source circuit conductors in conduit should be at least 8 times the diameter of the conductors to prevent damage to insulation.

    Open the full explanation page →

  3. Q3Which of the following is required when installing a roof-mounted PV array to maintain the fire classification of a roof?

    Show answer

    ✓ Correct answer: Providing a minimum 3-foot wide clear access pathway from eave to ridge

    To maintain a roof's fire classification, a minimum 3-foot wide clear access pathway from eave to ridge is required as per fire code requirements for PV installations.

    Open the full explanation page →

  4. Q4When installing a DC-coupled battery system with a PV array, what safety procedure is required before connecting the battery to the system?

    Show answer

    ✓ Correct answer: Verifying that all breakers and disconnects are in the open position

    Verifying that all breakers and disconnects are open is a critical safety procedure before connecting a battery to prevent unintended energization and potential electrical hazards.

    Open the full explanation page →

  5. Q5Which of the following markings is required on PV system disconnecting means according to NEC 2017?

    Show answer

    ✓ Correct answer: 'PV SYSTEM DISCONNECT'

    NEC 2017 requires that all PV system disconnecting means be permanently marked as 'PV SYSTEM DISCONNECT' for clear identification during maintenance or emergency situations.

    Open the full explanation page →

  6. Q6According to NFPA 70E, what is required for working on energized PV systems?

    Show answer

    ✓ Correct answer: An energized electrical work permit

    NFPA 70E requires an energized electrical work permit when working on energized PV systems to ensure proper risk assessment and safety protocols are followed.

    Open the full explanation page →

Unlock everything

Full Solar PV Professional Exam bank + unlimited mocks

Try 30 questions free. Unlock the complete Solar PV Professional Exam question bank, every explanation, and unlimited timed mock exams. Practice on any device.

Unlock Solar PV Professional Exam →
Cramming?
$2.99
/ week · per exam
Best value
$6.99
/ month · per exam