Free SMSTS Practice Test
Take a free SMSTS practice test for 2026 with questions, answers, explanations, PDF download and timed mock exam links.
SMSTS Questions
Open each answer, read the explanation, then continue into the full practice flow.
Q1You are managing a live construction site when a subcontractor begins hot works without a permit being issued, stating it is a routine task. What is the most appropriate action under health and safety legislation?
Show answer
✓ Correct answer: Stop the work immediately and ensure a permit-to-work system is followed
Hot works present significant fire risk and must be controlled through a permit-to-work system. The site manager has a legal duty to ensure safe systems of work are followed before allowing such activities. Why the other options are incorrect: • Allow the task to continue if a fire extinguisher is nearby: Fire-fighting equipment alone does not control ignition risks. • Permit the work provided it is completed quickly: Speed of work does not reduce fire risk. • Rely on the subcontractor’s insurance arrangements: Insurance does not remove the duty to prevent harm. • Ask the operative to carry out a dynamic risk assessment only: Dynamic assessment alone is insufficient for high-risk activities.
Q2You observe operatives working at height without proper edge protection because the task will only take a few minutes. What is the most appropriate response?
Show answer
✓ Correct answer: Stop the task and ensure suitable collective protection is installed
The Work at Height Regulations require risks to be avoided or controlled regardless of task duration. Collective protection must be prioritised, and unsafe work stopped immediately. Why the other options are incorrect: • Allow the work to continue due to its short duration: Duration does not reduce the legal requirement to manage fall risks. • Permit the work if operatives are wearing harnesses without anchor points: Harnesses without suitable anchorage do not provide effective protection. • Instruct operatives to proceed carefully: Care alone is not a control measure recognised by legislation. • Record the issue and discuss it at the next toolbox talk: Delaying action leaves workers exposed to immediate risk.
Q3You are the site manager on a refurbishment project. A subcontractor begins cutting concrete internally, generating significant dust. They state that operatives are wearing disposable masks so work can continue. As the manager, what is the most appropriate action under health and safety legislation?
Show answer
✓ Correct answer: Stop the work and ensure suitable control measures are implemented in line with COSHH before allowing it to continue
Under COSHH and the Health and Safety at Work etc. Act, exposure to hazardous substances such as respirable silica must be prevented or adequately controlled. The site manager has a duty to stop unsafe work and ensure suitable controls (e.g. extraction, wet cutting, appropriate RPE) are in place before work continues. Why the other options are incorrect: • Allow the work to continue as long as operatives are wearing any form of respiratory protection: Generic masks may be inadequate and do not remove the duty to properly assess and control exposure. • Ask the subcontractor to complete a method statement after the work has finished: Risk assessments and controls must be in place before work starts, not retrospectively. • Reduce the number of operatives in the area to limit exposure: Reducing numbers does not adequately control hazardous dust exposure. • Rely on the subcontractor to manage the risk as they are the employer: The principal contractor retains overall responsibility for site safety and cannot delegate it entirely.
Q4As a site manager, you are informed that a worker has a medical condition that could affect their safety while operating plant. How should you apply health and safety law?
Show answer
✓ Correct answer: Review suitability of the task and ensure reasonable controls are in place
Health and safety law requires risks to be assessed and managed while also considering equality and reasonable adjustments. The manager must ensure work remains safe. Why the other options are incorrect: • Remove the worker from site immediately without assessment: Immediate removal without assessment may be unreasonable and inappropriate. • Ignore the issue as it is a personal matter: Personal matters still become relevant if they affect site safety. • Allow the worker to decide whether they are fit to operate plant: Fitness for work cannot be left solely to individual judgement. • Only act if an incident occurs: Waiting for an incident breaches proactive legal duties.
Q5You identify poor housekeeping creating trip hazards across access routes. What action best aligns with legal requirements?
Show answer
✓ Correct answer: Stop work in the affected areas until housekeeping standards are restored
Health and safety law requires workplaces to be maintained in a safe condition. Poor housekeeping presents foreseeable risk and must be addressed immediately. Why the other options are incorrect: • Warn operatives to take extra care: Warnings alone do not remove physical hazards. • Address the issue at the next site meeting: Delaying action prolongs exposure to risk. • Rely on individuals to manage their own safety: Individuals cannot control site-wide hazards alone. • Allow work to continue to avoid delay: Programme pressures do not justify unsafe conditions.
Q6You are reviewing lifting operations planned by a subcontractor. The lift plan is generic and does not reflect site-specific constraints. What is the correct action?
Show answer
✓ Correct answer: Require the lift plan to be revised to reflect site-specific risks before approval
Health and safety law requires risks to be assessed in relation to the actual work environment. Generic plans do not adequately address site-specific hazards. Why the other options are incorrect: • Approve the plan as it meets minimum requirements: Minimum standards may still be insufficient for the site. • Allow the lift under additional supervision: Supervision cannot replace proper planning. • Proceed with the lift at a quieter time of day: Timing alone does not control lifting risks. • Accept the plan if it has been used on previous sites: Previous use does not guarantee suitability.
Q7A contractor plans to use a new chemical product on site. No safety data sheet has been provided. What should you do?
Show answer
✓ Correct answer: Prevent its use until the required information is reviewed and controls are agreed
COSHH requires assessment of hazardous substances before use. Without safety data and agreed controls, the product must not be used. Why the other options are incorrect: • Allow use if operatives have used similar products before: Similarity to other products does not remove the need for assessment. • Proceed with additional PPE as a precaution: PPE alone may not adequately control exposure. • Store the product away from other materials and continue work: Storage does not address the risks of use. • Ask the supplier for information after work has started: Controls must be established before exposure occurs.
Q8You are the site manager on a busy city-centre project. A subcontractor begins work without having received a site induction, stating they have worked on similar sites before. What is the most appropriate action under health and safety legislation?
Show answer
✓ Correct answer: Stop the work and ensure the subcontractor completes a site induction before continuing
Under the Health and Safety at Work etc. Act and CDM Regulations, those controlling work must ensure workers are provided with suitable information, instruction and training. A site induction is a fundamental legal control and work should not proceed without it. Why the other options are incorrect: • Allow work to continue under close supervision: Supervision does not replace the requirement for formal instruction and information. • Permit work to continue for low-risk activities only: Risk level does not remove the duty to provide adequate induction. • Issue a verbal briefing covering key site hazards: A brief verbal warning is insufficient as a structured induction. • Rely on the subcontractor’s employer to induct them: The principal contractor retains responsibility for site arrangements.
Q9A worker refuses to wear mandatory PPE provided on site. What is the most appropriate legal response?
Show answer
✓ Correct answer: Stop the worker from continuing the task until PPE is worn
Both employers and those in control of work have duties to ensure PPE is used where required. Allowing work to continue without PPE would breach health and safety law. Why the other options are incorrect: • Allow work to continue but issue a warning: Warnings without enforcement do not control risk. • Provide alternative PPE only if requested: Suitable PPE has already been provided. • Let the subcontractor deal with the issue later: Responsibility cannot be deferred when there is immediate risk. • Ignore the refusal if the task is low risk: Risk level does not remove mandatory PPE requirements.
Q10A subcontractor proposes a change to their method of work due to programme pressure, without updating their risk assessment. What should you do?
Show answer
✓ Correct answer: Require the risk assessment and method statement to be reviewed and approved before the change
Health and safety law requires risks to be assessed before work changes are implemented. Allowing unassessed changes would breach the duty to plan and manage work safely. Why the other options are incorrect: • Allow the change if the supervisor is competent: Competence does not replace the need for documented assessment. • Permit the change temporarily and review later: Temporary changes can still introduce significant risk. • Allow the change for non-critical tasks only: Task importance does not alter legal requirements. • Document the change in the site diary only: Recording alone does not control risk.
Full SMSTS bank + unlimited mocks
Try 30 questions free. Unlock the complete SMSTS question bank, every explanation, and unlimited timed mock exams. Practice on any device.
Unlock SMSTS →