A subcontractor proposes a change to their method of work due to programme pressure, without updating their risk assessment. What should you do?

Practise this SMSTS question free, then download the PDF, watch the video walkthrough, or unlock timed mock exams for the full web bank.
Download PDFWatch video
Multiple choice — select the best answer
✓ Correct answer: A. Require the risk assessment and method statement to be reviewed and approved before the change Health and safety law requires risks to be assessed before work changes are implemented. Allowing unassessed changes would breach the duty to plan and manage work safely. Why the other options are incorrect: • Allow the change if the supervisor is competent: Competence does not replace the need for documented assessment. • Permit the change temporarily and review later: Temporary changes can still introduce significant risk. • Allow the change for non-critical tasks only: Task importance does not alter legal requirements. • Document the change in the site diary only: Recording alone does not control risk.

Keep practising. Use the free SMSTS PDF, watch the YouTube walkthrough, or unlock all 10 web questions with timed mock exams.

Free PDFVideo walkthrough
Keep practising

Related questions

Free practice here. Timed mocks when you are ready.

Study the SMSTS Exam Prep 2026 free question explanations, download the PDF, then unlock timed mock exams on the web when you want exam-day practice.

Download PDFStart practice test