Free PMI PMP Exam App Practice Test PDF
Download a free PMI PMP Exam App practice test PDF with 30 questions, answers and explanations, then continue with online mock exams.
Free PMI PMP Exam App PDF with 30 questions
Print it, save it, or use it as a quick cram sheet before taking a timed mock exam.
Download PDF
The PDF includes 30 PMI PMP Exam App questions with answers and explanations.
Try PMI PMP Exam App questions now
Q1You are managing a construction project for a new community center. As you begin the Plan Quality Management process, which document is a key input you should consider?
Show answer
✓ Correct answer: Project management plan
Answer: Project management plan The project management plan is a key input for the Plan Quality Management process because it provides an overarching framework and contains other subsidiary plans that are necessary for developing the quality management processes. While the project schedule, risk register, and resource requirements are all valuable documents, they are not the primary frameworks necessary when initiating the Plan Quality Management process.
Q2The logistics coordinator for a virtual team event has received approval from all team leads to proceed with the new event plan. What is the next action the logistics coordinator should take?
Show answer
✓ Correct answer: Update event plan documentation and communicate updates
Answer: Update event plan documentation and communicate updates After obtaining approval for the new event plan, the next step is to ensure all relevant documents and the event plan are updated. This ensures transparency and alignment among all stakeholders before proceeding to the execution phase. This step is crucial to prevent misunderstandings and to secure commitment from all parties involved in the event process.
Q3You are leading a planning meeting for your startup's new mobile app. The team is undecided on how much effort it will take to integrate an augmented reality (AR) feature, as they have never worked with AR technology before. What is your best course of action to address this uncertainty?
Show answer
✓ Correct answer: Allocate time for a research phase to explore AR integration
Allocating time for a research phase or a spike allows the team to understand AR technology better, leading to more accurate estimates and informed decisions.
Q4Bill is enhancing the DevOps practices within his organization. Which of the following practices best align with the DevOps philosophy and are inspired by Extreme Programming (XP)?
Show answer
✓ Correct answer: Continuous integration, automated testing, pair programming, refactoring, and test-driven development
Answer: Continuous integration, automated testing, pair programming, refactoring, and test-driven development These practices are core elements of both DevOps and XP, focusing on automation and collaboration. All other answer options are incorrect as they do not align with key practices of XP or DevOps.
Q5Alex is managing a marketing campaign which is at its midpoint when a team member recommends a new approach to enhance engagement. This approach involves a change that includes extending research activities and utilizing different ad techniques. The team member suggests updating the scope and timeline to incorporate these tasks. Alex evaluates the impact on cost and schedule and drafts a change request, which the campaign steering committee approves. What should Alex do next? Task Current Duration (days) Suggested Duration (days) Research Market Trends 10 15 Design Ad Content 20 20 Deploy Campaign 5 5 Monitor Performance 5 5
Show answer
✓ Correct answer: Update the scope and schedule baselines to reflect the approved change before implementing it
Answer: Update the scope and schedule baselines to reflect the approved change before implementing it. The correct approach is to update the baselines before implementing any changes. This practice ensures that the campaign is tracked against the new scope and schedule, not former benchmarks. Assessing the impact of the change before implementation has already been completed. Implementing the change prior to baseline updates risks tracking with incorrect data. Updating the campaign strategy document is unnecessary without broader strategic shifts.
Q6A non-profit organization is managing an international conference project. The total budget authorized for this project is $300,000 and the project duration is 100 days. Work progress is distributed evenly over the schedule timeline. By day 25, the actual work completed is 15%. What is the Actual Cost (AC) incurred by day 25?
Show answer
✓ Correct answer: $45,000
The Actual Cost (AC) is calculated as the cost spent to complete work during a specific period. By day 25, they have completed 15% of the work as planned. Since the budget is evenly distributed, the AC is calculated as: $$300,000 \times 0.15 = 45,000$$. Therefore, the AC on day 25 is $45,000.
Full PMI PMP Exam App bank + unlimited mocks
Try 30 questions free. Unlock the complete PMI PMP Exam App question bank, every explanation, and unlimited timed mock exams. Practice on any device.
Unlock PMI PMP Exam App →