You are managing a construction project for a new community center. As you begin the Plan Quality Management process, which document is a key input you should consider?
Practise this PMI PMP Exam App question free, then download the PDF, watch the video walkthrough, or unlock timed mock exams for the full web bank.
✓ Correct answer: D. Project management planAnswer: Project management plan The project management plan is a key input for the Plan Quality Management process because it provides an overarching framework and contains other subsidiary plans that are necessary for developing the quality management processes. While the project schedule, risk register, and resource requirements are all valuable documents, they are not the primary frameworks necessary when initiating the Plan Quality Management process.