When advising on delivery methods for a complex hospital construction project with a tight timeline, which approach would likely best balance risk and schedule requirements?
Practise this PMI-CP Construction Prep question free, then download the PDF, watch the video walkthrough, or unlock timed mock exams for the full web bank.
AConstruction Manager at Risk (CM at Risk) with fast-tracking
BDesign-Bid-Build with multiple prime contractors
CDesign-Build with lowest bid selection
DIntegrated Project Delivery without BIM capabilities
✓ Correct answer: A. Construction Manager at Risk (CM at Risk) with fast-trackingCM at Risk with fast-tracking provides schedule advantages through overlapping design and construction phases while maintaining a single point of responsibility for construction, balancing the need for speed with appropriate risk management.
Keep practising. Use the free PMI-CP Construction Prep PDF, watch the YouTube walkthrough, or unlock all 10 web questions with timed mock exams.
Free practice here. Timed mocks when you are ready.
Study the PMI-CP Construction Prep free question explanations, download the PDF, then unlock timed mock exams on the web when you want exam-day practice.