During the procurement phase of a complex infrastructure project, what is the most effective way to allocate risk between the owner and contractor?
Practise this PMI-CP Construction Prep question free, then download the PDF, watch the video walkthrough, or unlock timed mock exams for the full web bank.
ADistribute risks equally between all parties regardless of management capability
BAssign each risk to the party best positioned to manage it
CTransfer all identifiable risks to the contractor with appropriate price premiums
DHave the owner retain all risks to keep contractor bids lower
✓ Correct answer: B. Assign each risk to the party best positioned to manage itAssigning risks to the party best able to manage them is the most effective allocation strategy as it improves project efficiency and reduces cost premiums associated with parties taking on risks they cannot effectively control.
Keep practising. Use the free PMI-CP Construction Prep PDF, watch the YouTube walkthrough, or unlock all 10 web questions with timed mock exams.
Free practice here. Timed mocks when you are ready.
Study the PMI-CP Construction Prep free question explanations, download the PDF, then unlock timed mock exams on the web when you want exam-day practice.