During contract administration for a large commercial building project, what is the most effective approach to manage contract changes?
Practise this PMI-CP Construction Prep question free, then download the PDF, watch the video walkthrough, or unlock timed mock exams for the full web bank.
ARejecting all changes not explicitly covered in the original scope
BImplementing a documented change management system with clear approval protocols
CAddressing changes informally through field directives
DCollecting all change requests for end-of-project negotiation
✓ Correct answer: B. Implementing a documented change management system with clear approval protocolsA documented change management system with clear approval protocols ensures proper evaluation, documentation, and implementation of changes while maintaining contractual compliance throughout the process.
Keep practising. Use the free PMI-CP Construction Prep PDF, watch the YouTube walkthrough, or unlock all 10 web questions with timed mock exams.
Free practice here. Timed mocks when you are ready.
Study the PMI-CP Construction Prep free question explanations, download the PDF, then unlock timed mock exams on the web when you want exam-day practice.