A construction project manager is developing a risk management plan for a high-rise building project. Which approach would be most effective for comprehensive risk identification?
Practise this PMI-CP Construction Prep question free, then download the PDF, watch the video walkthrough, or unlock timed mock exams for the full web bank.
ARelying solely on historical data from similar projects
BAssigning risk identification to the project controls team only
CUsing generic industry checklists without stakeholder input
DConducting collaborative risk identification workshops with cross-functional experts
✓ Correct answer: D. Conducting collaborative risk identification workshops with cross-functional expertsCollaborative workshops with cross-functional experts provide the most comprehensive approach to risk identification as they leverage diverse perspectives and expertise to identify a wider range of potential risks than individual methods.
Keep practising. Use the free PMI-CP Construction Prep PDF, watch the YouTube walkthrough, or unlock all 10 web questions with timed mock exams.
Free practice here. Timed mocks when you are ready.
Study the PMI-CP Construction Prep free question explanations, download the PDF, then unlock timed mock exams on the web when you want exam-day practice.