You are working on a project tasked with organizing a series of webinars for global participants. During a meeting with the project team, the project manager suggests using a particular webinar software to manage registrations and host sessions. Everyone agrees, and you immediately move to procure the software licenses and schedule training. Which of the following does this best describe?

Practise this PMI CAPM Project Mgmt Prep question free, then download the PDF, watch the video walkthrough, or unlock timed mock exams for the full web bank.
Multiple choice — select the best answer
✓ Correct answer: D. Communication technology Answer: Communication technology. Communication technology refers to the tools and systems, like webinar software in this instance, used to communicate information efficiently to project stakeholders. Factors influencing the choice include urgency, reliability, ease of use, and project-specific needs.

Keep practising. Use the free PMI CAPM Project Mgmt Prep PDF, watch the YouTube walkthrough, or unlock all 10 web questions with timed mock exams.

Keep practising

Related questions

Free practice here. Timed mocks when you are ready.

Study the PMI CAPM Project Mgmt Prep free question explanations, download the PDF, then unlock timed mock exams on the web when you want exam-day practice.