You are leading a project to implement a new customer relationship management (CRM) system. A new set of requirements has emerged. You need to identify who is responsible for managing these new requirements. Where would you find this information?

Practise this PMI CAPM Project Mgmt Prep question free, then download the PDF, watch the video walkthrough, or unlock timed mock exams for the full web bank.
Multiple choice — select the best answer
✓ Correct answer: C. Requirements traceability matrix Answer: Requirements traceability matrix. The requirements traceability matrix is a document that links requirements to project deliverables, ensuring that all requirements are addressed and accounted for. It typically includes information on who is responsible for each requirement, along with its current status and other essential details.

Keep practising. Use the free PMI CAPM Project Mgmt Prep PDF, watch the YouTube walkthrough, or unlock all 10 web questions with timed mock exams.

Keep practising

Related questions

Free practice here. Timed mocks when you are ready.

Study the PMI CAPM Project Mgmt Prep free question explanations, download the PDF, then unlock timed mock exams on the web when you want exam-day practice.