During a project review meeting focused on the development of the Project Management Plan, you notice a discrepancy in the listed outputs. Which of the following is not an output of the Develop Project Management Plan process?

Practise this PMI CAPM Project Mgmt Prep question free, then download the PDF, watch the video walkthrough, or unlock timed mock exams for the full web bank.
Multiple choice — select the best answer
✓ Correct answer: D. Expert judgment Answer: Expert judgment The outputs of the Develop Project Management Plan process include: 1. Project management plan 2. Project documents updates 3. Change requests Expert judgment is a tool or technique used in this process, not an output.

Keep practising. Use the free PMI CAPM Project Mgmt Prep PDF, watch the YouTube walkthrough, or unlock all 10 web questions with timed mock exams.

Keep practising

Related questions

Free practice here. Timed mocks when you are ready.

Study the PMI CAPM Project Mgmt Prep free question explanations, download the PDF, then unlock timed mock exams on the web when you want exam-day practice.