A project manager needs to update all team members about changes in the project schedule. The manager decides to use a method involving sending emails and calendar updates directly to each member to ensure they receive the information. What type of communication method does this best describe?

Practise this PMI CAPM Project Mgmt Prep question free, then download the PDF, watch the video walkthrough, or unlock timed mock exams for the full web bank.
Multiple choice — select the best answer
✓ Correct answer: A. Push communication Answer: Push communication Push communication involves sending information directly to specific stakeholders. The method ensures that the required information is sent but does not guarantee its understanding or acknowledgement by the recipient. Options such as emails and updates fall under push communication methods.

Keep practising. Use the free PMI CAPM Project Mgmt Prep PDF, watch the YouTube walkthrough, or unlock all 10 web questions with timed mock exams.

Keep practising

Related questions

Free practice here. Timed mocks when you are ready.

Study the PMI CAPM Project Mgmt Prep free question explanations, download the PDF, then unlock timed mock exams on the web when you want exam-day practice.