Alex is managing a construction project for a new office building. The project schedule shows a negative float, risking delay beyond the strict deadline set by stakeholders. What should Alex do first to address this issue?

Practise this PMI CAPM Project Mgmt Prep question free, then download the PDF, watch the video walkthrough, or unlock timed mock exams for the full web bank.
Multiple choice — select the best answer
✓ Correct answer: D. He should analyze the options of the negative float by compressing the schedule. To address a negative float, Alex should first analyze the schedule and explore options to compress it. This might involve fast-tracking certain tasks or reassigning resources to ensure the project is completed on time. The other options either do not directly address the delay or involve assumptions that might not be feasible.

Keep practising. Use the free PMI CAPM Project Mgmt Prep PDF, watch the YouTube walkthrough, or unlock all 10 web questions with timed mock exams.

Keep practising

Related questions

Free practice here. Timed mocks when you are ready.

Study the PMI CAPM Project Mgmt Prep free question explanations, download the PDF, then unlock timed mock exams on the web when you want exam-day practice.