AThe approved construction drawings and equipment submittals
BThe utility interconnection tariff schedule
CThe property survey and title report
DThe original equipment manufacturer warranty cards
✓ Correct answer: A. The approved construction drawings and equipment submittalsApproved construction drawings and equipment submittals establish what was engineered and what was approved by the AHJ. Comparing as-built conditions to these documents catches substitutions or omissions before the system is energized.