A project manager notices that a key stakeholder has not been responsive to the project updates shared via email. The delays in feedback are affecting the achievement of a critical milestone. What should the project manager do to resolve this issue efficiently?
Practise this PMI PMP Exam App question free, then download the PDF, watch the video walkthrough, or unlock timed mock exams for the full web bank.
ASchedule an in-person meeting with the stakeholder
BRemove the stakeholder from the communication loop
CWait for the stakeholder to respond at their convenience
DContinue with the project without stakeholder input
✓ Correct answer: A. Schedule an in-person meeting with the stakeholderThe project manager should directly engage with the stakeholder by scheduling an in-person meeting to address the communication gap and ensure the stakeholder understands their critical role in providing timely input for the project's success.
Keep practising. Use the free PMI PMP Exam App PDF, watch the YouTube walkthrough, or unlock all 10 web questions with timed mock exams.