ADirect the stakeholder to the Scrum board where sprint progress is visually displayed
BSchedule a one-on-one meeting to discuss the sprint details
CRefer the stakeholder to the Product Owner for a detailed progress update
DOffer to prepare a detailed report for the stakeholder by the end of the week
✓ Correct answer: A. Direct the stakeholder to the Scrum board where sprint progress is visually displayedAgile methodologies emphasize transparency and the use of visual tools such as Scrum boards or Kanban boards. These information radiators enable stakeholders to get an immediate understanding of the project's current status. Directing the stakeholder to the Scrum board maintains transparency and allows for real-time progress checking, fostering trust and efficient communication without the need for detailed meetings or reports.