An agile team is preparing for the upcoming sprint and needs to integrate potential risk responses alongside user stories and ongoing tasks in their planning. This integrated list helps prioritize tasks to deliver maximum customer value. What is this list called?

Practise this PMI ACP Exam App question free, then download the PDF, watch the video walkthrough, or unlock timed mock exams for the full web bank.
Multiple choice — select the best answer
✓ Correct answer: A. risk-adjusted backlog A risk-adjusted backlog includes not only the regular product backlog items like user stories and tasks but also risk responses. This ensures that the team is constantly aware of and dealing with risks along with regular items, providing a holistic prioritization based on value.

Keep practising. Use the free PMI ACP Exam App PDF, watch the YouTube walkthrough, or unlock all 10 web questions with timed mock exams.

Keep practising

Related questions

Free practice here. Timed mocks when you are ready.

Study the PMI ACP Exam App free question explanations, download the PDF, then unlock timed mock exams on the web when you want exam-day practice.