A dispute has arisen regarding differing site conditions on a transportation infrastructure project. Which resolution approach typically minimizes project disruption?

Practise this PMI-CP Construction Prep question free, then download the PDF, watch the video walkthrough, or unlock timed mock exams for the full web bank.
Multiple choice — select the best answer
✓ Correct answer: D. Structured negotiation with a dispute review board Structured negotiation with a dispute review board provides an efficient method for resolving contract disputes while minimizing project disruption, as it allows for timely expert review while keeping the parties engaged in direct communication.

Keep practising. Use the free PMI-CP Construction Prep PDF, watch the YouTube walkthrough, or unlock all 10 web questions with timed mock exams.

Keep practising

Related questions

Free practice here. Timed mocks when you are ready.

Study the PMI-CP Construction Prep free question explanations, download the PDF, then unlock timed mock exams on the web when you want exam-day practice.