Which of the following most clearly describes business-as-usual activity rather than project work?

Practise this APM PFQ question free, then download the PDF, watch the video walkthrough, or unlock timed mock exams for the full web bank.
Download PDFWatch video
Multiple choice — select the best answer
✓ Correct answer: C. Carrying out consistent, repeating tasks and services without interruption Business-as-usual involves sustaining routine, repeatable activities and services that keep the organisation running continuously. Why the other options are incorrect: • Completing a defined scope of work within a fixed schedule: Working within a defined scope and schedule is a hallmark of project management, not BAU. • Progressing through a structured series of phases to meet set objectives: Structured, phased life cycles are a feature of project delivery. • Maintaining a risk register to support short-term delivery goals: Risk registers are tools associated with project environments. • Producing one-off results using a dedicated set of resources: Producing unique, one-off outputs is what distinguishes projects from ongoing operations.

Keep practising. Use the free APM PFQ PDF, watch the YouTube walkthrough, or unlock all 10 web questions with timed mock exams.

Free PDFVideo walkthrough
Keep practising

Related questions

Free practice here. Timed mocks when you are ready.

Study the APM PFQ Exam Prep 2026 free question explanations, download the PDF, then unlock timed mock exams on the web when you want exam-day practice.

Download PDFStart practice test