ACompleting a defined scope of work within a fixed schedule
BProgressing through a structured series of phases to meet set objectives
CCarrying out consistent, repeating tasks and services without interruption
DMaintaining a risk register to support short-term delivery goals
EProducing one-off results using a dedicated set of resources
✓ Correct answer: C. Carrying out consistent, repeating tasks and services without interruptionBusiness-as-usual involves sustaining routine, repeatable activities and services that keep the organisation running continuously.
Why the other options are incorrect:
• Completing a defined scope of work within a fixed schedule: Working within a defined scope and schedule is a hallmark of project management, not BAU.
• Progressing through a structured series of phases to meet set objectives: Structured, phased life cycles are a feature of project delivery.
• Maintaining a risk register to support short-term delivery goals: Risk registers are tools associated with project environments.
• Producing one-off results using a dedicated set of resources: Producing unique, one-off outputs is what distinguishes projects from ongoing operations.
Keep practising. Use the free APM PFQ PDF, watch the YouTube walkthrough, or unlock all 10 web questions with timed mock exams.
Free practice here. Timed mocks when you are ready.
Study the APM PFQ Exam Prep 2026 free question explanations, download the PDF, then unlock timed mock exams on the web when you want exam-day practice.