AA software company managing a client's existing system throughout the year
BA hospital delivering round-the-clock emergency services
CAn IT team rolling out a new CRM platform over a six-month period
DA support desk team responding to user issues on an ongoing basis
EAn HR team processing staff payroll every week
✓ Correct answer: C. An IT team rolling out a new CRM platform over a six-month periodRolling out a CRM system within a set timeframe to meet a defined goal is a classic example of project work.
Why the other options are incorrect:
• A software company managing a client's existing system throughout the year: Year-round system maintenance is an operational, not project, activity.
• A hospital delivering round-the-clock emergency services: Providing emergency care continuously is business-as-usual.
• A support desk team responding to user issues on an ongoing basis: Ongoing support desk work is not project-based.
• An HR team processing staff payroll every week: Weekly payroll processing is routine operational activity.
Keep practising. Use the free APM PFQ PDF, watch the YouTube walkthrough, or unlock all 10 web questions with timed mock exams.
Free practice here. Timed mocks when you are ready.
Study the APM PFQ Exam Prep 2026 free question explanations, download the PDF, then unlock timed mock exams on the web when you want exam-day practice.