Which of the following gives the most accurate description of a project?

Practise this APM PFQ question free, then download the PDF, watch the video walkthrough, or unlock timed mock exams for the full web bank.
Download PDFWatch video
Multiple choice — select the best answer
✓ Correct answer: A. A time-limited undertaking established to produce a particular outcome A project has a clear start and finish and is set up to achieve specific goals within that timeframe. Why the other options are incorrect: • A continuous activity designed to sustain day-to-day business operations: Continuous operations describe business-as-usual, not a project. • A workflow dedicated exclusively to handling customer queries: Customer query handling is an ongoing function, not a project. • A division with fixed staffing and established responsibilities: A standing department with permanent roles is not a temporary initiative. • A risk-management programme running for more than twelve months: Risk management may feature within a project but does not itself define one.

Keep practising. Use the free APM PFQ PDF, watch the YouTube walkthrough, or unlock all 10 web questions with timed mock exams.

Free PDFVideo walkthrough
Keep practising

Related questions

Free practice here. Timed mocks when you are ready.

Study the APM PFQ Exam Prep 2026 free question explanations, download the PDF, then unlock timed mock exams on the web when you want exam-day practice.

Download PDFStart practice test