When reviewing utility interconnection requirements, which of the following is typically required for grid-connected PV systems?

Practise this Solar PV Design Exam Prep question free, then download the PDF, watch the video walkthrough, or unlock timed mock exams for the full web bank.
Multiple choice — select the best answer
✓ Correct answer: B. External disconnect switch An external disconnect switch is typically required by utilities to allow them to isolate the PV system from the grid during maintenance or emergency situations.