BA temporary team-based activity with repeatable outcomes
CA temporary organisation created to deliver change
DA department that produces regular reports
EAn informal effort to support users
✓ Correct answer: C. A temporary organisation created to deliver changeA project is defined in PRINCE2 as a temporary structure created to deliver business change.
Why the other options are incorrect:
• A long-term investment to maintain operations: Long-term investments relate to operations or programmes.
• A temporary team-based activity with repeatable outcomes: Projects aim for unique outcomes, not repeatable ones.
• A department that produces regular reports: Departments are operational units, not projects.
• An informal effort to support users: Informal efforts lack the structure of a PRINCE2 project.
Keep practising. Use the free PRINCE2 Foundation PDF, watch the YouTube walkthrough, or unlock all 10 web questions with timed mock exams.
Free practice here. Timed mocks when you are ready.
Study the PRINCE2 Foundation Exam 2026 free question explanations, download the PDF, then unlock timed mock exams on the web when you want exam-day practice.