✓ Correct answer: C. ScopeScope is one of the six key aspects of project performance managed in PRINCE2.
Why the other options are incorrect:
• Customer loyalty: Customer loyalty is a business outcome, not a PRINCE2 performance aspect.
• Team motivation: Motivation is important but not one of the six managed aspects.
• Marketing strategy: Marketing strategy is not within the scope of PRINCE2.
• Daily operations: Operations are outside the temporary nature of projects.