What is the primary goal of project schedule management?

Practise this PMI-SP Scheduling Prep question free, then download the PDF, watch the video walkthrough, or unlock timed mock exams for the full web bank.
Multiple choice — select the best answer
✓ Correct answer: C. Ensuring timely completion of the project Project schedule management focuses on defining, sequencing, and managing project tasks to ensure the timely completion of the project. While related elements such as costs, quality, and resources are important, the primary goal is to ensure that the project is completed within the set time schedule.

Keep practising. Use the free PMI-SP Scheduling Prep PDF, watch the YouTube walkthrough, or unlock all 10 web questions with timed mock exams.

Keep practising

Related questions

Free practice here. Timed mocks when you are ready.

Study the PMI-SP Scheduling Prep free question explanations, download the PDF, then unlock timed mock exams on the web when you want exam-day practice.