In the context of project management, what is the critical path?
Practise this PMI-SP Scheduling Prep question free, then download the PDF, watch the video walkthrough, or unlock timed mock exams for the full web bank.
BThe sequence of tasks that determines the minimum project duration.
CThe path containing the most expensive tasks.
DThe tasks selected by the project sponsor.
✓ Correct answer: B. The sequence of tasks that determines the minimum project duration.The critical path includes all tasks that directly impact the project duration. Delays in any of these tasks will cause delays in the overall project completion. It is essential for these tasks to be monitored carefully to meet the project deadline.