You are managing a construction project for a new highway, and the local government continues to introduce changes to the project design during its lifecycle. What is the main concern associated with this behavior?

Practise this PMI-RMP Exam Prep question free, then download the PDF, watch the video walkthrough, or unlock timed mock exams for the full web bank.
Multiple choice — select the best answer
✓ Correct answer: B. Scope instability Answer: Scope instability Despite well-organized project plans, introducing new design changes frequently can make the project scope unstable. While changes in the project design can lead to safety concerns and schedule delays, the primary risk here is related to the instability of the project scope. Environmental impact is not the primary concern in this scenario.

Keep practising. Use the free PMI-RMP Exam Prep PDF, watch the YouTube walkthrough, or unlock all 10 web questions with timed mock exams.

Keep practising

Related questions

Free practice here. Timed mocks when you are ready.

Study the PMI-RMP Exam Prep free question explanations, download the PDF, then unlock timed mock exams on the web when you want exam-day practice.