What steps should be taken when initial responses to identified project risks are documented, and at what stage are they considered for action?

Practise this PMI-RMP Exam Prep question free, then download the PDF, watch the video walkthrough, or unlock timed mock exams for the full web bank.
Multiple choice — select the best answer
✓ Correct answer: D. Initial responses are documented during risk identification and considered for action when appropriate. Answer: Initial responses are documented during risk identification and considered for action when appropriate. When a project risk is first identified, initial responses might also be defined. These responses are recorded during the risk identification process and may be considered for immediate implementation depending on the situation. If not acted upon immediately, these responses should be revisited during the Plan Risk Responses process to determine their relevance and possible implementation.

Keep practising. Use the free PMI-RMP Exam Prep PDF, watch the YouTube walkthrough, or unlock all 10 web questions with timed mock exams.

Keep practising

Related questions

Free practice here. Timed mocks when you are ready.

Study the PMI-RMP Exam Prep free question explanations, download the PDF, then unlock timed mock exams on the web when you want exam-day practice.