AInitial responses are actions taken immediately to eliminate all identified project risks.
BInitial responses should always be delayed until the end of the project.
CInitial responses are considered only during risk monitoring and control.
DInitial responses are documented during risk identification and considered for action when appropriate.
✓ Correct answer: D. Initial responses are documented during risk identification and considered for action when appropriate.Answer: Initial responses are documented during risk identification and considered for action when appropriate. When a project risk is first identified, initial responses might also be defined. These responses are recorded during the risk identification process and may be considered for immediate implementation depending on the situation. If not acted upon immediately, these responses should be revisited during the Plan Risk Responses process to determine their relevance and possible implementation.
Keep practising. Use the free PMI-RMP Exam Prep PDF, watch the YouTube walkthrough, or unlock all 10 web questions with timed mock exams.