How should a program manager respond when strategic objectives change during program execution?

Practise this PMI PgMP Program Prep question free, then download the PDF, watch the video walkthrough, or unlock timed mock exams for the full web bank.
Multiple choice — select the best answer
✓ Correct answer: A. Reassess and realign the program to support new strategic objectives When strategic objectives change, the program must be reassessed and potentially realigned to ensure it continues to support organizational goals. This may require adjustments to scope, deliverables, or even program continuation.

Keep practising. Use the free PMI PgMP Program Prep PDF, watch the YouTube walkthrough, or unlock all 10 web questions with timed mock exams.

Keep practising

Related questions

Free practice here. Timed mocks when you are ready.

Study the PMI PgMP Program Prep free question explanations, download the PDF, then unlock timed mock exams on the web when you want exam-day practice.